History
Past service disruptions and maintenance events
1–8 April 2013
Maintenance
2013-04-07T01:30:00.000+08:00 to 2013-04-07T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-04-07T01:30:00.000+08:00 to 2013-04-07T04:30:00.000+08:00
Maintenance
2013-04-08T01:30:00.000+08:00 to 2013-04-08T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-04-08T01:30:00.000+08:00 to 2013-04-08T04:30:00.000+08:00
Maintenance
2013-04-08T01:30:00.000+08:00 to 2013-04-08T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-04-08T01:30:00.000+08:00 to 2013-04-08T04:30:00.000+08:00
25 March – 1 April 2013
Maintenance
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
Maintenance
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
Maintenance
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-04-01T01:30:00.000+08:00 to 2013-04-01T04:30:00.000+08:00
18–25 March 2013
Maintenance
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
Maintenance
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
Maintenance
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-03-25T01:30:00.000+08:00 to 2013-03-25T04:30:00.000+08:00
11–18 March 2013
Maintenance
2013-03-17T05:30:00.000+08:00 to 2013-03-17T10:00:00.000+08:00
Completed
Cable Replacement Works for Circle Line
Power Fault
2013-03-17T05:30:00.000+08:00 to 2013-03-17T10:00:00.000+08:00
Maintenance
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
Maintenance
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
Maintenance
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-03-18T01:30:00.000+08:00 to 2013-03-18T04:30:00.000+08:00
4–11 March 2013
Maintenance
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
Maintenance
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
Maintenance
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-03-11T01:30:00.000+08:00 to 2013-03-11T04:30:00.000+08:00
25 February – 4 March 2013
Maintenance
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00
Completed
Planned track works from Khatib to Yio Chu Kang
Track Work
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00
Maintenance
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00
Completed
Planned track works affecting North-South Line from Admiralty to Sembawang
Track Work
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00
Maintenance
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00
Completed
Planned track works from Bukit Batok to Jurong East
Track Work
2013-03-04T01:30:00.000+08:00 to 2013-03-04T04:30:00.000+08:00