History

Past service disruptions and maintenance events

31 July – 7 August 2023

Maintenance
Completed

Early closure of train services on Bukit Panjang LRT


Track Work
2023-07-31T14:34:00.000+08:00 to 2023-08-01T00:00:00.000+08:00

24–31 July 2023

No incidents

All systems operated normally during this period

17–24 July 2023

Maintenance
Completed

Tunnel strengthening works affecting Circle Line services


Track Work
2023-06-11T00:00:00.000+08:00 to 2023-07-20T23:59:59.000+08:00

10–17 July 2023

Maintenance
Completed

Tunnel strengthening works affecting Circle Line services


Track Work
2023-06-11T00:00:00.000+08:00 to 2023-07-20T23:59:59.000+08:00

3–10 July 2023

Disruption
Resolved

Major service disruption between Tuas Link and Tuas West Road


Security
2023-07-05T05:32:16.000+08:00 to 2023-07-05T07:21:08.000+08:00
Maintenance
Completed

Tunnel strengthening works affecting Circle Line services


Track Work
2023-06-11T00:00:00.000+08:00 to 2023-07-20T23:59:59.000+08:00

26 June – 3 July 2023

Maintenance
Completed

Tunnel strengthening works affecting Circle Line services


Track Work
2023-06-11T00:00:00.000+08:00 to 2023-07-20T23:59:59.000+08:00