History

Past service disruptions and maintenance events

27 January – 3 February 2025

Maintenance
Completed

Bukit Panjang LRT services to end earlier


System Upgrade
2025-02-02T14:30:00.000+00:00 to 2025-02-02T16:00:00.000+00:00

20–27 January 2025

Maintenance
Completed

Bukit Panjang LRT services to end earlier


System Upgrade
2025-01-26T14:30:00.000+00:00 to 2025-01-26T16:00:00.000+00:00

13–20 January 2025

Maintenance
Completed

Bukit Panjang LRT services to end earlier


System Upgrade
2025-01-19T14:30:00.000+00:00 to 2025-01-19T16:00:00.000+00:00

6–13 January 2025

Disruption
Resolved

Service disruption on NSL between Marina South Pier and Bishan


Train Fault
2025-01-10T09:54:03.000+00:00 to 2025-01-10T10:40:33.000+00:00
Maintenance
Completed

Bukit Panjang LRT services to end earlier


System Upgrade
2025-01-12T14:30:00.000+00:00 to 2025-01-12T16:00:00.000+00:00

30 December 2024 – 6 January 2025

Disruption
Resolved

Thomson–East Coast Line service disruption


Train Fault
2025-01-02T11:38:58.000+00:00 to 2025-01-02T12:00:44.000+00:00
Maintenance
Completed

Bukit Panjang LRT services to end earlier


System Upgrade