History
Past service disruptions and maintenance events
28 April – 5 May 2025
Maintenance
2025-05-04T14:30:00.000+00:00 to 2025-05-04T16:00:00.000+00:00
Completed
Bukit Panjang LRT services to end earlier
System Upgrade
2025-05-04T14:30:00.000+00:00 to 2025-05-04T16:00:00.000+00:00
21–28 April 2025
Disruption
2025-04-22T23:20:51.000+00:00 to 2025-04-23T01:00:51.000+00:00
Resolved
Service disruption on the East West Line
Track Fault
2025-04-22T23:20:51.000+00:00 to 2025-04-23T01:00:51.000+00:00
Maintenance
2025-04-27T14:30:00.000+00:00 to 2025-04-27T16:00:00.000+00:00
Completed
Bukit Panjang LRT services to end earlier
System Upgrade
2025-04-27T14:30:00.000+00:00 to 2025-04-27T16:00:00.000+00:00
14–21 April 2025
Disruption
2025-04-16T03:25:54.000+00:00 to 2025-04-16T04:40:14.000+00:00
Resolved
15 mins delay on NSL due to track fault
Track Fault
2025-04-16T03:25:54.000+00:00 to 2025-04-16T04:40:14.000+00:00
Maintenance
2025-04-20T14:30:00.000+00:00 to 2025-04-20T16:00:00.000+00:00
Completed
Bukit Panjang LRT services to end earlier
System Upgrade
2025-04-20T14:30:00.000+00:00 to 2025-04-20T16:00:00.000+00:00
7–14 April 2025
Maintenance
2025-04-13T14:30:00.000+00:00 to 2025-04-13T16:00:00.000+00:00
Completed
Bukit Panjang LRT services to end earlier
System Upgrade
2025-04-13T14:30:00.000+00:00 to 2025-04-13T16:00:00.000+00:00
31 March – 7 April 2025
Disruption
2025-04-04T05:35:01.000+00:00 to 2025-04-04T08:11:34.000+00:00
Resolved
Track fault causing delays on East West Line
DelayTrack Fault
2025-04-04T05:35:01.000+00:00 to 2025-04-04T08:11:34.000+00:00
Maintenance
2025-04-06T14:30:00.000+00:00 to 2025-04-06T16:00:00.000+00:00
Completed
Bukit Panjang LRT services to end earlier
System Upgrade
2025-04-06T14:30:00.000+00:00 to 2025-04-06T16:00:00.000+00:00