History
Past service disruptions and maintenance events
22–29 December 2025
Disruption
2025-12-25T23:38:12.000+00:00 to 2025-12-26T00:13:10.000+00:00
Resolved
NSL Major delay - Ang Mo Kio to Woodlands
Train FaultDelay
2025-12-25T23:38:12.000+00:00 to 2025-12-26T00:13:10.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Maintenance
2025-12-27T15:00:00.000+00:00 to 2025-12-28T01:00:00.000+00:00
Completed
CCL Track Works - Weekend Early Closures (Stage 6)
Track Work
2025-12-27T15:00:00.000+00:00 to 2025-12-28T01:00:00.000+00:00
15–22 December 2025
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Maintenance
2025-12-20T15:00:00.000+00:00 to 2025-12-21T01:00:00.000+00:00
Completed
CCL Track Works - Weekend Early Closures (Stage 6)
Track Work
2025-12-20T15:00:00.000+00:00 to 2025-12-21T01:00:00.000+00:00
8–15 December 2025
Disruption
2025-12-08T00:12:14.000+00:00 to 2025-12-08T01:24:03.000+00:00
Resolved
CCL Delay - HarbourFront to Paya Lebar (Public Report)
Delay
2025-12-08T00:12:14.000+00:00 to 2025-12-08T01:24:03.000+00:00
Maintenance
2025-12-05T14:12:16.000+00:00 to 2025-12-08T16:00:00.000+00:00
Completed
EWL Track Testing & Depot Disconnection Preparations - Bedok/Kembangan to Changi Depot
Track Work
2025-12-05T14:12:16.000+00:00 to 2025-12-08T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Maintenance
2025-11-28T16:00:00.000+00:00 to 2025-12-08T16:00:00.000+00:00
Completed
EWL Track Work - Bedok–Tampines and Tanah Merah–Expo
Track Work
2025-11-28T16:00:00.000+00:00 to 2025-12-08T16:00:00.000+00:00
Maintenance
2025-12-13T15:00:00.000+00:00 to 2025-12-14T01:00:00.000+00:00
Completed
CCL Track Works - Weekend Early Closures (Stage 6)
Track Work
2025-12-13T15:00:00.000+00:00 to 2025-12-14T01:00:00.000+00:00
1–8 December 2025
Maintenance
2025-12-05T14:12:16.000+00:00 to 2025-12-08T16:00:00.000+00:00
Completed
EWL Track Testing & Depot Disconnection Preparations - Bedok/Kembangan to Changi Depot
Track Work
2025-12-05T14:12:16.000+00:00 to 2025-12-08T16:00:00.000+00:00
Disruption
2025-12-02T11:50:00.000+00:00 to 2025-12-02T13:15:00.000+00:00
Resolved
EWL Track Fault - near Aljunied
Track Fault
2025-12-02T11:50:00.000+00:00 to 2025-12-02T13:15:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Maintenance
2025-11-28T16:00:00.000+00:00 to 2025-12-08T16:00:00.000+00:00
Completed
EWL Track Work - Bedok–Tampines and Tanah Merah–Expo
Track Work
2025-11-28T16:00:00.000+00:00 to 2025-12-08T16:00:00.000+00:00
Infrastructure
2025-07-31T16:00:00.000+00:00 to 2025-11-30T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
NSL
Station Renovation
2025-07-31T16:00:00.000+00:00 to 2025-11-30T16:00:00.000+00:00
Infrastructure
2025-07-31T16:00:00.000+00:00 to 2025-11-30T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-07-31T16:00:00.000+00:00 to 2025-11-30T16:00:00.000+00:00
30 December 2024 – 6 January 2025
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
MRT Platform Screen Doors at Underground Stations to Undergo Renewal
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Infrastructure
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00
Completed
Lift Upgrades at Bukit Panjang LRT stations
Station Renovation
2025-11-30T16:00:00.000+00:00 to 2026-03-31T16:00:00.000+00:00