Disruption

Service disruption on East West Line

Started
28 Oct 2012, 2:06 pm
Resolved
28 Oct 2012, 2:21 pm
Duration
930 secs
Affected stations
Subtypes
Passenger Incident

Timeline

SMRT

[EWL] UPDATE: Free bus services have ceased. Affected passengers may seek a refund in the next 14 days at all SMRT MRT stations.

SMRT

[EWL] UPDATE: Service from #Queenstown to #OutramPark has resumed. Free bus bridging continues to be available at designated boarding points.

SMRT

[EWL] UPDATE: Service from Queenstown to Outram Park is temporarily unavailable. Free buses continue to be available at designated points.

Statistics

35
Stations affected
930 secs
Total duration
1
Lines affected