Disruption

Signalling system fault causing delays

Started
12 Jun 2017, 1:10 am
Resolved
12 Jun 2017, 1:47 am
Duration
2,206 secs
Affected stations
Subtypes
Signal Fault

Timeline

SMRT

[NSL] UPDATE: Trains are progressively returning to normal speed between #ChoaChuKang and #JurongEast.

SMRT

[NSL] UPDATE: Please expect about 10 minutes additional travel time between Choa Chu Kang and Jurong East due to a signalling system fault. Train service is still operating.

SMRT

[NSL]: Due to signalling system fault, please add 20 minutes travelling time between Choa Chu Kang and Jurong East. Train service is still available.

Statistics

26
Stations affected
2,206 secs
Total duration
1
Lines affected