Disruption

East West Line train fault causing delays

Started
5 Jul 2017, 11:02 am
Resolved
5 Jul 2017, 11:29 am
Duration
1,637 secs
Affected stations
Subtypes
Train Fault

Timeline

SMRT

[EWL] UPDATE: Train fault at #JooKoon has been cleared. Trains are progressively back to normal speed.

SMRT

[EWL] UPDATE: Please add 10 minutes travel time from Jurong East to JooKoon, due to an earlier train fault at JooKoon. Train service is available.

SMRT

[EWL]: Due to a train fault, please add 15 minutes travel time from #JurongEast to #JooKoon towards #JooKoon. Train service is available.

Statistics

33
Stations affected
1,637 secs
Total duration
1
Lines affected