Disruption

NEL service disruption due to signalling fault at Farrer Park

Started
8 May 2021, 11:47 pm
Resolved
9 May 2021, 12:43 am
Duration
3,353 secs
Affected stations
Subtypes
Signal FaultDelay

Timeline

SBS Transit

NEL service has resumed. Once again, we are sorry for the inconvenience caused.

SBS Transit

NEL service is delayed for both direction due to a signalling fault at Farrer Park NE8. Additional travel time of about 15 minutes may be expected. We are sorry for the inconvenience caused.

SBS Transit

NEL service is delayed for both direction due to a signalling fault at Farrer Park NE8. Additional travel time of about 10 minutes may be expected. We are sorry for the inconvenience caused.

Statistics

16
Stations affected
3,353 secs
Total duration
1
Lines affected