Disruption perkhidmatan Bukit Panjang LRT disebabkan oleh arus elektrik
Dimulakan
3 Jul 2025, 1:24 PG
Diselesaikan
3 Jul 2025, 3:30 PG
Tempoh
7,560 saat
Stesen Terjejas
Subjenis
Gangguan Bekalan Elektrik
Timeline
MyTransport SG
11.30am: BPLRT - Train service is progressively returning to normal. Free regular buses and bridging buses are still available at the designated bus stops outside the stations.
MyTransport SG
11.20am: BPLRT - Due to a power fault, train service is not available at all stations. Free regular buses and bridging buses are available at the designated bus stops outside the stations.
MyTransport SG
9.50am: BPLRT - Due to a power fault, train service is not available at all stations. Free regular buses or bridging buses are available at the designated bus stops outside the stations.