What stood out
One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Bishan and Dhoby Ghaut.
The week at a glance
From 19–25 Sept 2011, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 15 hours 28 minutes in total.
Disruptions
1
Total disruption time
15 hours 28 minutes
Lines affected
1
How the week unfolded
Disruptions by day
- 0Mon
- 1Tue
- 0Wed
- 0Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Circle Line | 1 | 15 hours 28 minutes |
What happened
Longest disruptions first
- Power fault disrupts Circle Line →15 hours 28 minutes
CCL