mrtdown · The weekly brief

Week of 5 March 2012

5–11 Mar 2012

What stood out

One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Buona Vista and City Hall.

The week at a glance

From 5–11 Mar 2012, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 18 hours 38 minutes in total.

Disruptions

2

Unchanged from last week

Total disruption time

18 hours 38 minutes

17 hours 44 minutes more than last week

Lines affected

1

1 fewer than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 1Wed
  • 1Thu
  • 0Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
East-West Line218 hours 38 minutes

What happened

Longest disruptions first

  1. EWL

  2. EWL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:13 pm (Singapore time). How we count