mrtdown · The weekly brief
Week of 2 April 2012
2–8 Apr 2012
What stood out
2 recorded disruptions overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Bishan and Choa Chu Kang.
The week at a glance
From 2–8 Apr 2012, we recorded 3 disruptions on Singapore’s MRT and LRT network, lasting 1 hour 59 minutes in total.
Disruptions
3
3 more than last week
Total disruption time
1 hour 59 minutes
1 hour 59 minutes more than last week
Lines affected
3
3 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 1Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 1Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North-South Line | 1 | 1 hour 21 minutes |
| Circle Line | 1 | 27 minutes |
| East-West Line | 1 | 11 minutes |
What happened
Longest disruptions first
- South-bound train service disrupted due to track fault →1 hour 21 minutes
NSL
CCL
EWL