The week at a glance
From 9–15 Jul 2012, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 15 hours 45 minutes in total.
Disruptions
2
1 more than last week
Total disruption time
15 hours 45 minutes
15 hours 22 minutes more than last week
Lines affected
1
Unchanged from last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 1Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| East-West Line | 2 | 15 hours 45 minutes |
What happened
Longest disruptions first
- Eastbound trains from Tanjong Pagar to City Hall moving slower →15 hours 17 minutes