What stood out
Recorded disruptions included suspended service on parts of North East Line. Affected sections included the interchanges at Dhoby Ghaut and HarbourFront.
The week at a glance
From 7–13 Jan 2013, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 6 hours 22 minutes in total.
Disruptions
1
2 fewer than last week
Total disruption time
6 hours 22 minutes
5 minutes more than last week
Lines affected
1
2 fewer than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North East Line | 1 | 6 hours 22 minutes |
What happened
Longest disruptions first
- Train service delayed due to power fault →6 hours 22 minutes
NEL