mrtdown · The weekly brief
Week of 1 July 2013
1–7 Jul 2013
What stood out
2 recorded disruptions overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Buona Vista and Bishan.
The week at a glance
From 1–7 Jul 2013, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 2 hours 25 minutes in total.
The week also included 1 planned maintenance event.
Disruptions
2
1 more than last week
Total disruption time
2 hours 25 minutes
2 hours 14 minutes more than last week
Lines affected
2
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 2Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Bukit Panjang LRT | 1 | 2 hours 5 minutes |
| Circle Line | 1 | 20 minutes |
What happened
Longest disruptions first
- BPLRT train service disruption →2 hours 5 minutes
BPLRT
CCL