What stood out

2 recorded disruptions overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Buona Vista and Bishan.

The week at a glance

From 1–7 Jul 2013, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 2 hours 25 minutes in total.

The week also included 1 planned maintenance event.

Disruptions

2

1 more than last week

Total disruption time

2 hours 25 minutes

2 hours 14 minutes more than last week

Lines affected

2

1 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 0Wed
  • 2Thu
  • 0Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
Bukit Panjang LRT12 hours 5 minutes
Circle Line120 minutes

What happened

Longest disruptions first

  1. BPLRT

  2. CCL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.