mrtdown · The weekly brief

Week of 7 October 2013

7–13 Oct 2013

What stood out

Recorded disruptions included suspended service on parts of East-West Line. One incident accounted for 68% of recorded disruption time.

The week at a glance

From 7–13 Oct 2013, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 2 hours 13 minutes in total.

Disruptions

2

Unchanged from last week

Total disruption time

2 hours 13 minutes

1 hour 48 minutes more than last week

Lines affected

1

1 fewer than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 1Wed
  • 0Thu
  • 1Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
East-West Line22 hours 13 minutes

What happened

Longest disruptions first

  1. EWL

  2. EWL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:14 pm (Singapore time). How we count