mrtdown · The weekly brief

Week of 28 October 2013

28 Oct – 3 Nov 2013

What stood out

Affected sections included the interchanges at Dhoby Ghaut and Paya Lebar. Circle Line had a recorded disruption after 4 full weeks without one.

The week at a glance

From 28 Oct – 3 Nov 2013, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 1 hour 25 minutes in total.

Disruptions

2

2 more than last week

Total disruption time

1 hour 25 minutes

1 hour 25 minutes more than last week

Lines affected

2

2 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 0Wed
  • 1Thu
  • 1Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
East-West Line11 hour 8 minutes
Circle Line117 minutes

What happened

Longest disruptions first

  1. EWL

  2. CCL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:14 pm (Singapore time). How we count