mrtdown · The weekly brief
Week of 24 March 2014
24–30 Mar 2014
What stood out
3 recorded disruptions overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Buona Vista and Bishan.
The week at a glance
From 24–30 Mar 2014, we recorded 5 disruptions on Singapore’s MRT and LRT network, lasting 1 hour 51 minutes in total.
Disruptions
5
5 more than last week
Total disruption time
1 hour 51 minutes
1 hour 51 minutes more than last week
Lines affected
3
3 more than last week
How the week unfolded
Disruptions by day
- 1Mon
- 0Tue
- 1Wed
- 0Thu
- 2Fri
- 0Sat
- 1Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| East-West Line | 2 | 57 minutes |
| North-South Line | 2 | 47 minutes |
| Circle Line | 1 | 7 minutes |
What happened
Longest disruptions first
EWL
- Train Fault on North-South Line →28 minutes
NSL
NSL
EWL
- Train Fault at Circle Line →7 minutes
CCL