What stood out
Affected sections included the interchanges at Bishan and Choa Chu Kang. 100% of recorded disruption time fell on Saturday or Sunday.
The week at a glance
From 8–14 Sept 2014, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 19 minutes in total.
Disruptions
1
Unchanged from last week
Total disruption time
19 minutes
5 minutes more than last week
Lines affected
1
Unchanged from last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 0Thu
- 0Fri
- 1Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North-South Line | 1 | 19 minutes |
What happened
Longest disruptions first
- Major delays on North-South Line →19 minutes
NSL