mrtdown · The weekly brief
Week of 8 December 2014
8–14 Dec 2014
What stood out
One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Jurong East.
The week at a glance
From 8–14 Dec 2014, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 9 minutes in total.
Disruptions
1
1 more than last week
Total disruption time
9 minutes
9 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| East-West Line | 1 | 9 minutes |
What happened
Longest disruptions first
- Train Fault at Joo Koon →9 minutes
EWL