mrtdown · The weekly brief

Week of 28 March 2016

28 Mar – 3 Apr 2016

What stood out

Recorded disruptions included suspended service on parts of Sengkang LRT. Affected sections included the interchanges at Sengkang.

The week at a glance

From 28 Mar – 3 Apr 2016, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 10 minutes in total.

The week also included 1 planned maintenance event.

Disruptions

1

3 fewer than last week

Total disruption time

10 minutes

1 hour 56 minutes less than last week

Lines affected

1

1 fewer than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 1Tue
  • 0Wed
  • 0Thu
  • 0Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
Sengkang LRT110 minutes

What happened

Longest disruptions first

  1. SKLRT

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:52 pm (Singapore time). How we count