mrtdown · The weekly brief

Week of 9 January 2017

9–15 Jan 2017

What stood out

Recorded disruptions included suspended service on parts of Punggol LRT. Affected sections included the interchanges at Bishan and Punggol.

The week at a glance

From 9–15 Jan 2017, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 20 hours 59 minutes in total.

Disruptions

2

1 more than last week

Total disruption time

20 hours 59 minutes

20 hours 8 minutes more than last week

Lines affected

2

1 more than last week

How the week unfolded

Disruptions by day

  • 1Mon
  • 0Tue
  • 0Wed
  • 0Thu
  • 1Fri
  • 1Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
North-South Line120 hours 38 minutes
Punggol LRT121 minutes

What happened

Longest disruptions first

  1. NSL

  2. PGLRT

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:13 pm (Singapore time). How we count