mrtdown · The weekly brief
Week of 4 September 2017
4–10 Sept 2017
What stood out
Recorded disruptions included suspended service on parts of Bukit Panjang LRT. Affected sections included the interchanges at Bukit Panjang and Choa Chu Kang.
The week at a glance
From 4–10 Sept 2017, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 5 hours 33 minutes in total.
The week also included 1 planned maintenance event.
Disruptions
1
1 fewer than last week
Total disruption time
5 hours 33 minutes
38 minutes more than last week
Lines affected
1
1 fewer than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 0Thu
- 0Fri
- 1Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Bukit Panjang LRT | 1 | 5 hours 33 minutes |
What happened
Longest disruptions first
- No train service due to train fault →5 hours 33 minutes
BPLRT