Recorded disruptions included suspended service on parts of North-South Line. Affected sections included the interchanges at Bishan and Choa Chu Kang.

The week at a glance

From 2–8 Oct 2017, we recorded 4 disruptions on Singapore’s MRT and LRT network, lasting 6 hours 9 minutes in total.

Disruptions

4

3 more than last week

Total disruption time

6 hours 9 minutes

3 hours 25 minutes more than last week

Lines affected

2

1 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 1Tue
  • 1Wed
  • 0Thu
  • 0Fri
  • 1Sat
  • 1Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
North-South Line24 hours 19 minutes
North East Line21 hour 50 minutes

What happened

Longest disruptions first

  1. NSL

  2. NEL

  3. NEL

  4. NSL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.