What stood out
Recorded disruptions included suspended service on parts of Bukit Panjang LRT. Affected sections included the interchanges at Bukit Panjang and Choa Chu Kang.
The week at a glance
From 15–21 Jan 2018, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 43 minutes in total.
The week also included 1 planned maintenance event.
Disruptions
1
1 fewer than last week
Total disruption time
43 minutes
4 hours 15 minutes less than last week
Lines affected
1
1 fewer than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Bukit Panjang LRT | 1 | 43 minutes |
What happened
Longest disruptions first
BPLRT