What stood out
Recorded disruptions included suspended service on parts of Bukit Panjang LRT. Affected sections included the interchanges at Bugis and Bukit Panjang.
The week at a glance
From 14–20 May 2018, we recorded 3 disruptions on Singapore’s MRT and LRT network, lasting 4 hours 19 minutes in total.
Disruptions
3
3 more than last week
Total disruption time
4 hours 19 minutes
4 hours 19 minutes more than last week
Lines affected
3
3 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 1Thu
- 1Fri
- 1Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North-South Line | 1 | 2 hours 17 minutes |
| Bukit Panjang LRT | 1 | 1 hour 35 minutes |
| East-West Line | 1 | 27 minutes |
What happened
Longest disruptions first
NSL
- Service disruption on Bukit Panjang LRT →1 hour 35 minutes
BPLRT
EWL