mrtdown · The weekly brief
Week of 18 June 2018
18–24 Jun 2018
What stood out
Recorded disruptions included suspended service on parts of Bukit Panjang LRT. Affected sections included the interchanges at Bukit Panjang and Choa Chu Kang.
The week at a glance
From 18–24 Jun 2018, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 57 minutes in total.
The week also included 1 planned maintenance event.
Disruptions
1
1 more than last week
Total disruption time
57 minutes
57 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 0Thu
- 0Fri
- 1Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Bukit Panjang LRT | 1 | 57 minutes |
What happened
Longest disruptions first
BPLRT