mrtdown · The weekly brief
Week of 11 January 2021
11–17 Jan 2021
What stood out
Affected sections included the interchanges at Chinatown and Dhoby Ghaut. North East Line had a recorded disruption after 4 full weeks without one.
The week at a glance
From 11–17 Jan 2021, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 8 minutes in total.
The week also included 2 planned maintenance events.
Disruptions
1
Unchanged from last week
Total disruption time
8 minutes
51 minutes less than last week
Lines affected
1
Unchanged from last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 0Thu
- 1Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North East Line | 1 | 8 minutes |
What happened
Longest disruptions first
- NEL service disruption →8 minutes
NEL