What stood out
Affected sections included the interchanges at Bayfront and Buona Vista. Circle Line had a recorded disruption after 4 full weeks without one.
The week at a glance
From 15–21 Feb 2021, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 1 hour 19 minutes in total.
The week also included 2 planned maintenance events.
Disruptions
1
1 more than last week
Total disruption time
1 hour 19 minutes
1 hour 19 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 1Wed
- 0Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Circle Line | 1 | 1 hour 19 minutes |
What happened
Longest disruptions first
- Power Fault on Circle Line →1 hour 19 minutes
CCL