What stood out
Planned maintenance on Thomson–East Coast Line included service closures or changes to operating hours. Affected sections included the interchanges at Buona Vista and Botanic Gardens.
The week at a glance
From 26 Jul – 1 Aug 2021, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 1 hour 7 minutes in total.
The week also included 3 planned maintenance events.
Disruptions
1
1 more than last week
Total disruption time
1 hour 7 minutes
1 hour 7 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Circle Line | 1 | 1 hour 7 minutes |
What happened
Longest disruptions first
- Train fault causing delays on Circle Line →1 hour 7 minutes
CCL