mrtdown · The weekly brief
Week of 30 August 2021
30 Aug – 5 Sept 2021
What stood out
One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Bugis and Buona Vista.
The week at a glance
From 30 Aug – 5 Sept 2021, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 1 hour 0 minutes in total.
The week also included 1 planned maintenance event.
Disruptions
2
1 more than last week
Total disruption time
1 hour 0 minutes
2 hours 49 minutes less than last week
Lines affected
2
1 more than last week
How the week unfolded
Disruptions by day
- 1Mon
- 0Tue
- 0Wed
- 1Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| East-West Line | 1 | 31 minutes |
| North East Line | 1 | 29 minutes |
What happened
Longest disruptions first
- Train Fault on East West Line →31 minutes
EWL
- North East Line service disruption →29 minutes
NEL