mrtdown · The weekly brief

Week of 20 December 2021

20–26 Dec 2021

What stood out

Recorded disruptions included suspended service on parts of East-West Line. Affected sections included the interchanges at Choa Chu Kang and Jurong East.

The week at a glance

From 20–26 Dec 2021, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 1 hour 10 minutes in total.

Disruptions

2

2 more than last week

Total disruption time

1 hour 10 minutes

1 hour 10 minutes more than last week

Lines affected

2

2 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 0Wed
  • 0Thu
  • 1Fri
  • 1Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
East-West Line136 minutes
North-South Line134 minutes

What happened

Longest disruptions first

  1. EWL

  2. NSL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:15 pm (Singapore time). How we count