mrtdown · The weekly brief

Week of 19 September 2022

19–25 Sept 2022

What stood out

Recorded disruptions included suspended service on parts of Bukit Panjang LRT. Affected sections included the interchanges at Bukit Panjang and Bishan.

The week at a glance

From 19–25 Sept 2022, we recorded 2 disruptions on Singapore’s MRT and LRT network, lasting 6 hours 42 minutes in total.

The week also included 2 planned maintenance events.

Disruptions

2

1 more than last week

Total disruption time

6 hours 42 minutes

6 hours 7 minutes more than last week

Lines affected

2

1 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 2Wed
  • 0Thu
  • 0Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
Bukit Panjang LRT15 hours 45 minutes
North-South Line157 minutes

What happened

Longest disruptions first

  1. BPLRT

  2. NSL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:15 pm (Singapore time). How we count