mrtdown · The weekly brief

Week of 6 February 2023

6–12 Feb 2023

What stood out

3 recorded disruptions overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time). Affected sections included the interchanges at Bishan and Choa Chu Kang.

The week at a glance

From 6–12 Feb 2023, we recorded 3 disruptions on Singapore’s MRT and LRT network, lasting 8 hours 38 minutes in total.

Disruptions

3

2 more than last week

Total disruption time

8 hours 38 minutes

7 hours 12 minutes more than last week

Lines affected

2

1 more than last week

How the week unfolded

Disruptions by day

  • 2Mon
  • 0Tue
  • 1Wed
  • 0Thu
  • 0Fri
  • 0Sat
  • 0Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
North-South Line27 hours 49 minutes
Thomson–East Coast Line149 minutes

What happened

Longest disruptions first

  1. NSL

  2. NSL

  3. TEL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:15 pm (Singapore time). How we count