What stood out
Recorded disruptions included suspended service on parts of North-South Line. North-South Line had a recorded disruption after 4 full weeks without one.
The week at a glance
From 23–29 Oct 2023, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 1 hour 54 minutes in total.
Disruptions
1
1 more than last week
Total disruption time
1 hour 54 minutes
1 hour 54 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 0Tue
- 0Wed
- 0Thu
- 1Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| North-South Line | 1 | 1 hour 54 minutes |
What happened
Longest disruptions first
- Novena Station Closed Due to Incident →1 hour 54 minutes
NSL