What stood out
Planned maintenance on Circle Line included service closures or changes to operating hours. One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time).
The week at a glance
From 3–9 Nov 2025, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 12 hours 35 minutes in total.
The week also included 1 planned maintenance event. 1 infrastructure issue was active during the week.
Disruptions
1
Unchanged from last week
Total disruption time
12 hours 35 minutes
10 hours 21 minutes more than last week
Lines affected
1
Unchanged from last week
How the week unfolded
Disruptions by day
- 0Mon
- 1Tue
- 0Wed
- 0Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Bukit Panjang LRT | 1 | 12 hours 35 minutes |
What happened
Longest disruptions first
- BPLRT Passenger Fell onto Tracks - Bangkit Station →12 hours 35 minutes
BPLRT