What stood out
Planned maintenance on Circle Line included service closures or changes to operating hours. One recorded disruption overlapped weekday peak hours (7–9 am or 5–7 pm, Singapore time).
The week at a glance
From 17–23 Nov 2025, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 38 minutes in total.
The week also included 1 planned maintenance event. 1 infrastructure issue was active during the week.
Disruptions
1
1 more than last week
Total disruption time
38 minutes
38 minutes more than last week
Lines affected
1
1 more than last week
How the week unfolded
Disruptions by day
- 0Mon
- 1Tue
- 0Wed
- 0Thu
- 0Fri
- 0Sat
- 0Sun
Across the network
| Line | Disruptions | Duration |
|---|---|---|
| Thomson–East Coast Line | 1 | 38 minutes |
What happened
Longest disruptions first
- Train Fault on Thomson–East Coast Line →38 minutes