mrtdown · The weekly brief

Week of 27 April 2026

27 Apr – 3 May 2026

What stood out

Planned maintenance on Circle Line and Sengkang LRT included service closures or changes to operating hours. Affected sections included the interchanges at Caldecott and Orchard.

The week at a glance

From 27 Apr – 3 May 2026, we recorded 1 disruption on Singapore’s MRT and LRT network, lasting 2 hours 0 minutes in total.

The week also included 3 planned maintenance events. 3 infrastructure issues were active during the week.

Disruptions

1

1 more than last week

Total disruption time

2 hours 0 minutes

2 hours 0 minutes more than last week

Lines affected

1

1 more than last week

How the week unfolded

Disruptions by day

  • 0Mon
  • 0Tue
  • 0Wed
  • 0Thu
  • 0Fri
  • 0Sat
  • 1Sun

Across the network

Lines affected by recorded disruptions, longest total duration first
LineDisruptionsDuration
Thomson–East Coast Line12 hours 0 minutes

What happened

Longest disruptions first

  1. TEL

Monday–Sunday, Singapore time. Based on recorded incidents; missing reports may leave gaps. Maintenance is counted separately.

About these numbers

Each disruption counts once per week, even if it spans several days. We add up the time each disruption lasted within the week, so overlapping disruptions count separately. A disruption affecting several lines appears under each one. Total disruption time is not passenger delay. Past reports may change when records are corrected.

Updated 14 Oct 2026, 05:53 pm (Singapore time). How we count